North "A" Street construction has began!

Create: 06/06/2017 - 15:00

Contractors have started a mill and overlay project on North "A" Street (North Highway 81). 

Beginning on Monday ~ June 5, 2017, the Street Department will complete street maintenance
on North “A” Street from the Roundabout North to Hillside. This will consist of milling 2" off the
surface, which will take approximately two (2) days (weather-permitting).
 
2" of hot mix asphalt will then be applied over the milled surface, which will take approximately
an additional two (2) days (weather-permitting).
 
We anticipate this work will be completed by Friday ~ June 9th.
 
Formore information, please contact the Street Department at 326-7831.